The cost of federal permitting delays in all 50 states:

Alabama:

  • $20.6 BILLION: total value of Alabama projects stuck in the federal permitting process right now.
  • $36.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Alabama
  • The total economic impact of Alabama projects entering the federal permitting process annually is equivalent to 3.6% of Alabama’s total GDP.
  • $363 MILLION: total cost of federal permitting delays to Alabama manufacturers annually.

Alaska:

  • $20.6 BILLION: total value of Wyoming projects stuck in the federal permitting process right now.
  • $29.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Wyoming.
  • The total economic impact of Wyoming projects entering the federal permitting process annually is equivalent to 17.9% of Wyoming’s total GDP.
  • $35 MILLION: total cost of federal permitting delays to Wyoming manufacturers annually.

Arizona:

  • $59.7 BILLION: total value of Arizona projects stuck in the federal permitting process right now.
  • $143.2 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Arizona.
  • The total economic impact of Arizona projects entering the federal permitting process annually is equivalent to 5.2% of Arizona’s total GDP.
  • $115 MILLION: total cost of federal permitting delays to Arizona manufacturers annually.

Arkansas:

  • $23.6 BILLION: total value of Arkansas projects stuck in the federal permitting process right now.
  • $39.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Arkansas.
  • The total economic impact of Arkansas projects entering the federal permitting process annually is equivalent to 5.0% of Arkansas’s total GDP.
  • $188 MILLION: total cost of federal permitting delays to Arkansas manufacturers annually.

California:

  • $100.8 BILLION: total value of California projects stuck in the federal permitting process right now.
  • $262 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in California.
  • The total economic impact of California projects entering the federal permitting process annually is equivalent to 1.8% of California’s total GDP.
  • $1 BILLION: total cost of federal permitting delays to California manufacturers annually.

Colorado:

  • $26.5 BILLION: total value of Colorado projects stuck in the federal permitting process right now.
  • $59.7 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Colorado.
  • The total economic impact of Colorado projects entering the federal permitting process annually is equivalent to 4% of Colorado’s total GDP.
  • $121 MILLION: total cost of federal permitting delays to Colorado manufacturers annually.

Connecticut:

  • $13.8 BILLION: total value of Connecticut projects stuck in the federal permitting process right now.
  • $25.4 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Connecticut.
  • The total economic impact of Connecticut projects entering the federal permitting process annually is equivalent to 2.1% of Connecticut’s total GDP.
  • $111 MILLION: total cost of federal permitting delays to Connecticut manufacturers annually.

Delaware:

  • $4.9 BILLION: total value of Delaware projects stuck in the federal permitting process right now.
  • $8.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Delaware.
  • The total economic impact of Delaware projects entering the federal permitting process annually is equivalent to 2.3% of Delaware’s total GDP.
  • $35 MILLION: total cost of federal permitting delays to Delaware manufacturers annually.

Florida:

  • $80.5 BILLION: total value of Florida projects stuck in the federal permitting process right now.
  • $198.7 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Florida.
  • The total economic impact of Florida projects entering the federal permitting process annually is equivalent to 3.2% of Florida’s total GDP.
  • $368 MILLION: total cost of federal permitting delays to Florida manufacturers annually.

Georgia:

  • $34.6 BILLION: total value of Georgia projects stuck in the federal permitting process right now.
  • $76.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Georgia.
  • The total economic impact of Georgia projects entering the federal permitting process annually is equivalent to 2.8% of Georgia’s total GDP.
  • $360 MILLION: total cost of federal permitting delays to Georgia manufacturers annually.

Hawaii:

  • $4.3 BILLION: total value of Hawaii projects stuck in the federal permitting process right now.
  • $8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Hawaii.
  • The total economic impact of Hawaii projects entering the federal permitting process annually is equivalent to 1.6% of Hawaii’s total GDP.
  • $15 MILLION: total cost of federal permitting delays to Hawaii manufacturers annually.

Idaho:

  • $17.3 BILLION: total value of Idaho projects stuck in the federal permitting process right now
  • The total economic impact of Idaho projects entering the federal permitting process annually is equivalent to 5.7% of Idaho’s total GDP.
  • $32 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Idaho
  • $67 MILLION: total cost of federal permitting delays to Idaho manufacturers annually.

Illinois:

  • $46.4 BILLION: total value of Illinois projects stuck in the federal permitting process right now.
  • $104.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Illinois.
  • The total economic impact of Illinois projects entering the federal permitting process annually is equivalent to 2.8% of Illinois’s total GDP.
  • $503 MILLION: total cost of federal permitting delays to Illinois manufacturers annually.

Indiana:

  • $31.4 BILLION: total value of Indiana projects stuck in the federal permitting process right now.
  • $57.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Indiana.
  • The total economic impact of Indiana projects entering the federal permitting process annually is equivalent to 3.8% of Indiana’s total GDP.
  • $564 MILLION: total cost of federal permitting delays to Indiana manufacturers annually.

Iowa:

  • $16.8 BILLION: total value of Iowa projects stuck in the federal permitting process right now.
  • $29.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Iowa.
  • The total economic impact of Iowa projects entering the federal permitting process annually is equivalent to 3.6% of Iowa’s total GDP.
  • $280 MILLION: total cost of federal permitting delays to Iowa manufacturers annually.

Kansas:

  • $25.3 BILLION: total value of Kansas projects stuck in the federal permitting process right now.
  • $45.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Kansas.
  • The total economic impact of Kansas projects entering the federal permitting process annually is equivalent to 6.8% of Kansas’s total GDP.
  • $148 MILLION: total cost of federal permitting delays to Kansas manufacturers annually.

Kentucky:

  • $24.8 BILLION: total value of Kentucky projects stuck in the federal permitting process right now.
  • $41.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Kentucky.
  • The total economic impact of Kentucky projects entering the federal permitting process annually is equivalent to 4.5% of Kentucky’s total GDP.
  • $295 MILLION: total cost of federal permitting delays to Kentucky manufacturers annually.

Louisiana:

  • $41.9 BILLION: total value of Louisiana projects stuck in the federal permitting process right now
  • $75.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Louisiana
  • The total economic impact of Louisiana projects entering the federal permitting process annually is equivalent to 7.2% of Louisiana’s total GDP
  • $368 MILLION: total cost of federal permitting delays to Louisiana manufacturers annually

Maine:

  • $7.5 BILLION: total value of Maine projects stuck in the federal permitting process right now.
  • $13.7 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Maine.
  • The total economic impact of Maine projects entering the federal permitting process annually is equivalent to 3.7% of Maine’s total GDP.
  • $74 MILLION: total cost of federal permitting delays to Maine manufacturers annually.

Maryland:

  • $14.1 BILLION: total value of Maryland projects stuck in the federal permitting process right now.
  • $25.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Maryland.
  • The total economic impact of Maryland projects entering the federal permitting process annually is equivalent to 1.3% of Maryland’s total GDP.
  • $79 MILLION: total cost of federal permitting delays to Maryland manufacturers annually.

Massachusetts:

  • $16.3 BILLION: total value of Massachusetts projects stuck in the federal permitting process right now.
  • $34 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Massachusetts.
  • The total economic impact of Massachusetts entering the federal permitting process annually is equivalent to 1.4% of Massachusetts’s total GDP.
  • $192 MILLION: total cost of federal permitting delays to Massachusetts manufacturers annually.

Michigan:

  • $56.1 BILLION: total value of Michigan projects stuck in the federal permitting process right now.
  • $116.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Michigan.
  • The total economic impact of Michigan projects entering the federal permitting process annually is equivalent to 5.1% of Michigan’s total GDP.
  • $357 MILLION: total cost of federal permitting delays to Michigan manufacturers annually.

Minnesota:

  • $28.3 BILLION: total value of Minnesota projects stuck in the federal permitting process right now.
  • $61.4 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Minnesota.
  • The total economic impact of Minnesota projects entering the federal permitting process annually is equivalent to 3.4% of Minnesota’s total GDP.
  • $220 MILLION: total cost of federal permitting delays to Minnesota manufacturers annually.

Mississippi:

  • $16.9 BILLION: total value of Mississippi projects stuck in the federal permitting process right now.
  • $26.9 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Mississippi.
  • The total economic impact of Mississippi projects entering the federal permitting process annually is equivalent to 5% of Mississippi’s total GDP.
  • $177 MILLION: total cost of federal permitting delays to Mississippi manufacturers annually.

Missouri:

  • $26.4 BILLION: total value of Missouri projects stuck in the federal permitting process right now.
  • $50.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Missouri.
  • The total economic impact of Missouri projects entering the federal permitting process annually is equivalent to 3.6% of Missouri’s total GDP.
  • $243 MILLION: total cost of federal permitting delays to Missouri manufacturers annually.

Montana:

  • $24.8 BILLION: total value of Kentucky projects stuck in the federal permitting process right now.
  • $41.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Kentucky.
  • The total economic impact of Kentucky projects entering the federal permitting process annually is equivalent to 4.5% of Kentucky’s total GDP.
  • $295 MILLION: total cost of federal permitting delays to Kentucky manufacturers annually.

Nebraska:

  • $13.5 BILLION: total value of Nebraska projects stuck in the federal permitting process right now,
  • $25.2 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Nebraska,
  • The total economic impact of Nebraska projects entering the federal permitting process annually is equivalent to 3.8% of Nebraska’s total GDP.
  • $113 MILLION: total cost of federal permitting delays to Nebraska manufacturers annually.

Nevada:

  • $25.1 BILLION: total value of Nevada projects stuck in the federal permitting process right now.
  • $48.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Nevada.
  • The total economic impact of Nevada projects entering the federal permitting process annually is equivalent to 3.8% of Nevada’s total GDP.
  • $49 MILLION: total cost of federal permitting delays to Nevada manufacturers annually.

New Hampshire:

  • $4.9 BILLION: total value of New Hampshire projects stuck in the federal permitting process right now.
  • $8.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in New Hampshire.
  • The total economic impact of New Hampshire projects entering the federal permitting process annually is equivalent to 1.8% of New Hampshire’s total GDP.
  • $53 MILLION: total cost of federal permitting delays to New Hampshire manufacturers annually.

New Jersey:

  • $31.4 BILLION: total value of New Jersey projects stuck in the federal permitting process right now.
  • $61.2 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in New Jersey.
  • The total economic impact of New Jersey projects entering the federal permitting process annually is equivalent to 2.3% of New Jersey’s total GDP.
  • $186 MILLION: total cost of federal permitting delays to New Jersey manufacturers annually.

New Mexico:

  • $43.9 BILLION: total value of New Mexico projects stuck in the federal permitting process right now.
  • $71.4 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in New Mexico.
  • The total economic impact of New Mexico projects entering the federal permitting process annually is equivalent to 24.2% of New Mexico’s total GDP.
  • $28 MILLION: total cost of federal permitting delays to New Mexico manufacturers annually.

New York:

  • $61.3 BILLION: total value of New York projects stuck in the federal permitting process right now.
  • $122.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in New York.
  • The total economic impact of New York projects entering the federal permitting process annually is equivalent to 1.4% of New York’s total GDP.
  • $306 MILLION: total cost of federal permitting delays to New York manufacturers annually.

North Carolina:

  • $50.6 BILLION: total value of North Carolina projects stuck in the federal permitting process right now.
  • $104.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in North Carolina.
  • The total economic impact of North Carolina projects entering the federal permitting process annually is equivalent to 3.5% of North Carolina’s total GDP.
  • $385 MILLION: total cost of federal permitting delays to North Carolina manufacturers annually.

North Dakota:

  • $24 BILLION: total value of North Dakota projects stuck in the federal permitting process right now.
  • $39 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in North Dakota.
  • The total economic impact of North Dakota projects entering the federal permitting process annually is equivalent to 23.1% of North Dakota’s total GDP.
  • $41 MILLION: total cost of federal permitting delays to North Dakota manufacturers annually.

Ohio:

  • $45.1 BILLION: total value of Ohio projects stuck in the federal permitting process right now.
  • $93.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Ohio.
  • The total economic impact of Ohio projects entering the federal permitting process annually is equivalent to 3.6% of Ohio’s total GDP.
  • $669 MILLION: total cost of federal permitting delays to Ohio manufacturers annually.

Oklahoma:

  • $29.7 BILLION: total value of Oklahoma projects stuck in the federal permitting process right now.
  • $55 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Oklahoma.
  • The total economic impact of Oklahoma projects entering the federal permitting process annually is equivalent to 7.3% of Oklahoma’s total GDP.
  • $161 MILLION: total cost of federal permitting delays to Oklahoma manufacturers annually.

Oregon:

  • $21 BILLION: total value of Oregon projects stuck in the federal permitting process right now.
  • $43.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Oregon.
  • The total economic impact of Oregon projects entering the federal permitting process annually is equivalent to 3.4% of Oregon’s total GDP.
  • $173 MILLION: total cost of federal permitting delays to Oregon manufacturers annually.

Pennsylvania:

  • $54.3 BILLION: total value of Pennsylvania projects stuck in the federal permitting process right now.
  • $109.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Pennsylvania.
  • The total economic impact of Pennsylvania projects entering the federal permitting process annually is equivalent to 3.8% of Pennsylvania’s total GDP.
  • $506 MILLION: total cost of federal permitting delays to Pennsylvania manufacturers annually.

Rhode Island:

  • $5.8 BILLION: total value of Rhode Island projects stuck in the federal permitting process right now.
  • $10.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Rhode Island.
  • The total economic impact of Rhode Island projects entering the federal permitting process annually is equivalent to 3.2% of Rhode Island’s total GDP.
  • $29 MILLION: total cost of federal permitting delays to Rhode Island manufacturers annually.

South Carolina:

  • $22.6 BILLION: total value of South Carolina projects stuck in the federal permitting process right now.
  • $45.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in South Carolina.
  • The total economic impact of South Carolina projects entering the federal permitting process annually is equivalent to 4% of South Carolina’s total GDP.
  • $310 MILLION: total cost of federal permitting delays to South Carolina manufacturers annually.

South Dakota:

  • $9.7 BILLION: total value of South Dakota projects stuck in the federal permitting process right now.
  • $16.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in South Dakota.
  • The total economic impact of South Dakota projects entering the federal permitting process annually is equivalent to 5.5% of South Dakota’s total GDP.
  • $48 MILLION: total cost of federal permitting delays to South Dakota manufacturers annually.

Tennessee:

  • $24.6 BILLION: total value of Tennessee projects stuck in the federal permitting process right now.
  • $47.2 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Tennessee.
  • The total economic impact of Tennessee projects entering the federal permitting process annually is equivalent to 2.5% of Tennessee’s total GDP.
  • $322 MILLION: total cost of federal permitting delays to Tennessee manufacturers annually.

Texas:

  • $373.3 BILLION: total value of Texas projects stuck in the federal permitting process right now.
  • $924.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Texas.
  • The total economic impact of Texas projects entering the federal permitting process annually is equivalent to 11.6% of Texas’s total GDP.
  • $1.4 BILLION: total cost of federal permitting delays to Texas manufacturers annually.

Utah:

  • $25 BILLION: total value of Utah projects stuck in the federal permitting process right now.
  • $54.4 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Utah.
  • The total economic impact of Utah projects entering the federal permitting process annually is equivalent to 5.2% of Utah’s total GDP.
  • $87 MILLION: total cost of federal permitting delays to Utah manufacturers annually.

Vermont:

  • $3.4 BILLION: total value of Vermont projects stuck in the federal permitting process right now.
  • $5.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Vermont.
  • The total economic impact of Vermont projects entering the federal permitting process annually is equivalent to 3.1% of Vermont’s total GDP.
  • $29 MILLION: total cost of federal permitting delays to Vermont manufacturers annually.

Virginia:

  • $37.3 BILLION: total value of Virginia projects stuck in the federal permitting process right now.
  • $66.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Virginia.
  • The total economic impact of Virginia projects entering the federal permitting process annually is equivalent to 2.3% of Virginia’s total GDP.
  • $199 MILLION: total cost of federal permitting delays to Virginia manufacturers annually.

Washington:

  • $30.2 BILLION: total value of Washington projects stuck in the federal permitting process right now.
  • $63.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Washington.
  • The total economic impact of Washington projects entering the federal permitting process annually is equivalent to 2.2% of Washington’s total GDP.
  • $196 MILLION: total cost of federal permitting delays to Washington manufacturers annually.

West Virginia:

  • $22.3 BILLION: total value of West Virginia projects stuck in the federal permitting process right now.
  • $32.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in West Virginia.
  • The total economic impact of West Virginia projects entering the federal permitting process annually is equivalent to 9.4% of West Virginia’s total GDP.
  • $87 MILLION: total cost of federal permitting delays to West Virginia manufacturers annually.

Wisconsin:

  • $24 BILLION: total value of Wisconsin projects stuck in the federal permitting process right now.
  • $46.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Wisconsin.
  • The total economic impact of Wisconsin projects entering the federal permitting process annually is equivalent to 3.4% of Wisconsin’s total GDP.
  • $339 MILLION: total cost of federal permitting delays to Wisconsin manufacturers annually.

Wyoming:

  • $20.6 BILLION: total value of Wyoming projects stuck in the federal permitting process right now.
  • $29.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Wyoming.
  • The total economic impact of Wyoming projects entering the federal permitting process annually is equivalent to 17.9% of Wyoming’s total GDP.
  • $35 MILLION: total cost of federal permitting delays to Wyoming manufacturers annually.

Nationwide:

  • $240-280 BILLION in new investments begin the federal permitting process each year
  • The current 4-5 year federal permitting decision timeline results in $1.7-2.4 TRILLION in unrealized economic benefit annually
  • $1.1-1.5 TRILLION in investments are sitting on the sidelines waiting for permitting decisions
  • $12.1 BILLION: total cost of federal permitting delays to America’s manufacturers annually

Sources: