The cost of federal permitting delays in all 50 states:
- $20.6 BILLION: total value of Alabama projects stuck in the federal permitting process right now.
- $36.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Alabama
- The total economic impact of Alabama projects entering the federal permitting process annually is equivalent to 3.6% of Alabama’s total GDP.
- $363 MILLION: total cost of federal permitting delays to Alabama manufacturers annually.
- $20.6 BILLION: total value of Wyoming projects stuck in the federal permitting process right now.
- $29.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Wyoming.
- The total economic impact of Wyoming projects entering the federal permitting process annually is equivalent to 17.9% of Wyoming’s total GDP.
- $35 MILLION: total cost of federal permitting delays to Wyoming manufacturers annually.
- $59.7 BILLION: total value of Arizona projects stuck in the federal permitting process right now.
- $143.2 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Arizona.
- The total economic impact of Arizona projects entering the federal permitting process annually is equivalent to 5.2% of Arizona’s total GDP.
- $115 MILLION: total cost of federal permitting delays to Arizona manufacturers annually.
- $23.6 BILLION: total value of Arkansas projects stuck in the federal permitting process right now.
- $39.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Arkansas.
- The total economic impact of Arkansas projects entering the federal permitting process annually is equivalent to 5.0% of Arkansas’s total GDP.
- $188 MILLION: total cost of federal permitting delays to Arkansas manufacturers annually.
- $100.8 BILLION: total value of California projects stuck in the federal permitting process right now.
- $262 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in California.
- The total economic impact of California projects entering the federal permitting process annually is equivalent to 1.8% of California’s total GDP.
- $1 BILLION: total cost of federal permitting delays to California manufacturers annually.
- $26.5 BILLION: total value of Colorado projects stuck in the federal permitting process right now.
- $59.7 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Colorado.
- The total economic impact of Colorado projects entering the federal permitting process annually is equivalent to 4% of Colorado’s total GDP.
- $121 MILLION: total cost of federal permitting delays to Colorado manufacturers annually.
- $13.8 BILLION: total value of Connecticut projects stuck in the federal permitting process right now.
- $25.4 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Connecticut.
- The total economic impact of Connecticut projects entering the federal permitting process annually is equivalent to 2.1% of Connecticut’s total GDP.
- $111 MILLION: total cost of federal permitting delays to Connecticut manufacturers annually.
- $4.9 BILLION: total value of Delaware projects stuck in the federal permitting process right now.
- $8.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Delaware.
- The total economic impact of Delaware projects entering the federal permitting process annually is equivalent to 2.3% of Delaware’s total GDP.
- $35 MILLION: total cost of federal permitting delays to Delaware manufacturers annually.
- $80.5 BILLION: total value of Florida projects stuck in the federal permitting process right now.
- $198.7 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Florida.
- The total economic impact of Florida projects entering the federal permitting process annually is equivalent to 3.2% of Florida’s total GDP.
- $368 MILLION: total cost of federal permitting delays to Florida manufacturers annually.
- $34.6 BILLION: total value of Georgia projects stuck in the federal permitting process right now.
- $76.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Georgia.
- The total economic impact of Georgia projects entering the federal permitting process annually is equivalent to 2.8% of Georgia’s total GDP.
- $360 MILLION: total cost of federal permitting delays to Georgia manufacturers annually.
- $4.3 BILLION: total value of Hawaii projects stuck in the federal permitting process right now.
- $8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Hawaii.
- The total economic impact of Hawaii projects entering the federal permitting process annually is equivalent to 1.6% of Hawaii’s total GDP.
- $15 MILLION: total cost of federal permitting delays to Hawaii manufacturers annually.
- $17.3 BILLION: total value of Idaho projects stuck in the federal permitting process right now
- The total economic impact of Idaho projects entering the federal permitting process annually is equivalent to 5.7% of Idaho’s total GDP.
- $32 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Idaho
- $67 MILLION: total cost of federal permitting delays to Idaho manufacturers annually.
- $46.4 BILLION: total value of Illinois projects stuck in the federal permitting process right now.
- $104.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Illinois.
- The total economic impact of Illinois projects entering the federal permitting process annually is equivalent to 2.8% of Illinois’s total GDP.
- $503 MILLION: total cost of federal permitting delays to Illinois manufacturers annually.
- $31.4 BILLION: total value of Indiana projects stuck in the federal permitting process right now.
- $57.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Indiana.
- The total economic impact of Indiana projects entering the federal permitting process annually is equivalent to 3.8% of Indiana’s total GDP.
- $564 MILLION: total cost of federal permitting delays to Indiana manufacturers annually.
Iowa:
- $16.8 BILLION: total value of Iowa projects stuck in the federal permitting process right now.
- $29.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Iowa.
- The total economic impact of Iowa projects entering the federal permitting process annually is equivalent to 3.6% of Iowa’s total GDP.
- $280 MILLION: total cost of federal permitting delays to Iowa manufacturers annually.
- $25.3 BILLION: total value of Kansas projects stuck in the federal permitting process right now.
- $45.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Kansas.
- The total economic impact of Kansas projects entering the federal permitting process annually is equivalent to 6.8% of Kansas’s total GDP.
- $148 MILLION: total cost of federal permitting delays to Kansas manufacturers annually.
- $24.8 BILLION: total value of Kentucky projects stuck in the federal permitting process right now.
- $41.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Kentucky.
- The total economic impact of Kentucky projects entering the federal permitting process annually is equivalent to 4.5% of Kentucky’s total GDP.
- $295 MILLION: total cost of federal permitting delays to Kentucky manufacturers annually.
- $41.9 BILLION: total value of Louisiana projects stuck in the federal permitting process right now
- $75.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Louisiana
- The total economic impact of Louisiana projects entering the federal permitting process annually is equivalent to 7.2% of Louisiana’s total GDP
- $368 MILLION: total cost of federal permitting delays to Louisiana manufacturers annually
- $7.5 BILLION: total value of Maine projects stuck in the federal permitting process right now.
- $13.7 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Maine.
- The total economic impact of Maine projects entering the federal permitting process annually is equivalent to 3.7% of Maine’s total GDP.
- $74 MILLION: total cost of federal permitting delays to Maine manufacturers annually.
- $14.1 BILLION: total value of Maryland projects stuck in the federal permitting process right now.
- $25.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Maryland.
- The total economic impact of Maryland projects entering the federal permitting process annually is equivalent to 1.3% of Maryland’s total GDP.
- $79 MILLION: total cost of federal permitting delays to Maryland manufacturers annually.
- $16.3 BILLION: total value of Massachusetts projects stuck in the federal permitting process right now.
- $34 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Massachusetts.
- The total economic impact of Massachusetts entering the federal permitting process annually is equivalent to 1.4% of Massachusetts’s total GDP.
- $192 MILLION: total cost of federal permitting delays to Massachusetts manufacturers annually.
- $56.1 BILLION: total value of Michigan projects stuck in the federal permitting process right now.
- $116.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Michigan.
- The total economic impact of Michigan projects entering the federal permitting process annually is equivalent to 5.1% of Michigan’s total GDP.
- $357 MILLION: total cost of federal permitting delays to Michigan manufacturers annually.
- $28.3 BILLION: total value of Minnesota projects stuck in the federal permitting process right now.
- $61.4 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Minnesota.
- The total economic impact of Minnesota projects entering the federal permitting process annually is equivalent to 3.4% of Minnesota’s total GDP.
- $220 MILLION: total cost of federal permitting delays to Minnesota manufacturers annually.
- $16.9 BILLION: total value of Mississippi projects stuck in the federal permitting process right now.
- $26.9 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Mississippi.
- The total economic impact of Mississippi projects entering the federal permitting process annually is equivalent to 5% of Mississippi’s total GDP.
- $177 MILLION: total cost of federal permitting delays to Mississippi manufacturers annually.
- $26.4 BILLION: total value of Missouri projects stuck in the federal permitting process right now.
- $50.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Missouri.
- The total economic impact of Missouri projects entering the federal permitting process annually is equivalent to 3.6% of Missouri’s total GDP.
- $243 MILLION: total cost of federal permitting delays to Missouri manufacturers annually.
- $24.8 BILLION: total value of Kentucky projects stuck in the federal permitting process right now.
- $41.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Kentucky.
- The total economic impact of Kentucky projects entering the federal permitting process annually is equivalent to 4.5% of Kentucky’s total GDP.
- $295 MILLION: total cost of federal permitting delays to Kentucky manufacturers annually.
- $13.5 BILLION: total value of Nebraska projects stuck in the federal permitting process right now,
- $25.2 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Nebraska,
- The total economic impact of Nebraska projects entering the federal permitting process annually is equivalent to 3.8% of Nebraska’s total GDP.
- $113 MILLION: total cost of federal permitting delays to Nebraska manufacturers annually.
- $25.1 BILLION: total value of Nevada projects stuck in the federal permitting process right now.
- $48.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Nevada.
- The total economic impact of Nevada projects entering the federal permitting process annually is equivalent to 3.8% of Nevada’s total GDP.
- $49 MILLION: total cost of federal permitting delays to Nevada manufacturers annually.
- $4.9 BILLION: total value of New Hampshire projects stuck in the federal permitting process right now.
- $8.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in New Hampshire.
- The total economic impact of New Hampshire projects entering the federal permitting process annually is equivalent to 1.8% of New Hampshire’s total GDP.
- $53 MILLION: total cost of federal permitting delays to New Hampshire manufacturers annually.
- $31.4 BILLION: total value of New Jersey projects stuck in the federal permitting process right now.
- $61.2 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in New Jersey.
- The total economic impact of New Jersey projects entering the federal permitting process annually is equivalent to 2.3% of New Jersey’s total GDP.
- $186 MILLION: total cost of federal permitting delays to New Jersey manufacturers annually.
- $43.9 BILLION: total value of New Mexico projects stuck in the federal permitting process right now.
- $71.4 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in New Mexico.
- The total economic impact of New Mexico projects entering the federal permitting process annually is equivalent to 24.2% of New Mexico’s total GDP.
- $28 MILLION: total cost of federal permitting delays to New Mexico manufacturers annually.
- $61.3 BILLION: total value of New York projects stuck in the federal permitting process right now.
- $122.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in New York.
- The total economic impact of New York projects entering the federal permitting process annually is equivalent to 1.4% of New York’s total GDP.
- $306 MILLION: total cost of federal permitting delays to New York manufacturers annually.
- $50.6 BILLION: total value of North Carolina projects stuck in the federal permitting process right now.
- $104.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in North Carolina.
- The total economic impact of North Carolina projects entering the federal permitting process annually is equivalent to 3.5% of North Carolina’s total GDP.
- $385 MILLION: total cost of federal permitting delays to North Carolina manufacturers annually.
- $24 BILLION: total value of North Dakota projects stuck in the federal permitting process right now.
- $39 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in North Dakota.
- The total economic impact of North Dakota projects entering the federal permitting process annually is equivalent to 23.1% of North Dakota’s total GDP.
- $41 MILLION: total cost of federal permitting delays to North Dakota manufacturers annually.
Ohio:
- $45.1 BILLION: total value of Ohio projects stuck in the federal permitting process right now.
- $93.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Ohio.
- The total economic impact of Ohio projects entering the federal permitting process annually is equivalent to 3.6% of Ohio’s total GDP.
- $669 MILLION: total cost of federal permitting delays to Ohio manufacturers annually.
- $29.7 BILLION: total value of Oklahoma projects stuck in the federal permitting process right now.
- $55 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Oklahoma.
- The total economic impact of Oklahoma projects entering the federal permitting process annually is equivalent to 7.3% of Oklahoma’s total GDP.
- $161 MILLION: total cost of federal permitting delays to Oklahoma manufacturers annually.
- $21 BILLION: total value of Oregon projects stuck in the federal permitting process right now.
- $43.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Oregon.
- The total economic impact of Oregon projects entering the federal permitting process annually is equivalent to 3.4% of Oregon’s total GDP.
- $173 MILLION: total cost of federal permitting delays to Oregon manufacturers annually.
- $54.3 BILLION: total value of Pennsylvania projects stuck in the federal permitting process right now.
- $109.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Pennsylvania.
- The total economic impact of Pennsylvania projects entering the federal permitting process annually is equivalent to 3.8% of Pennsylvania’s total GDP.
- $506 MILLION: total cost of federal permitting delays to Pennsylvania manufacturers annually.
- $5.8 BILLION: total value of Rhode Island projects stuck in the federal permitting process right now.
- $10.1 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Rhode Island.
- The total economic impact of Rhode Island projects entering the federal permitting process annually is equivalent to 3.2% of Rhode Island’s total GDP.
- $29 MILLION: total cost of federal permitting delays to Rhode Island manufacturers annually.
- $22.6 BILLION: total value of South Carolina projects stuck in the federal permitting process right now.
- $45.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in South Carolina.
- The total economic impact of South Carolina projects entering the federal permitting process annually is equivalent to 4% of South Carolina’s total GDP.
- $310 MILLION: total cost of federal permitting delays to South Carolina manufacturers annually.
- $9.7 BILLION: total value of South Dakota projects stuck in the federal permitting process right now.
- $16.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in South Dakota.
- The total economic impact of South Dakota projects entering the federal permitting process annually is equivalent to 5.5% of South Dakota’s total GDP.
- $48 MILLION: total cost of federal permitting delays to South Dakota manufacturers annually.
- $24.6 BILLION: total value of Tennessee projects stuck in the federal permitting process right now.
- $47.2 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Tennessee.
- The total economic impact of Tennessee projects entering the federal permitting process annually is equivalent to 2.5% of Tennessee’s total GDP.
- $322 MILLION: total cost of federal permitting delays to Tennessee manufacturers annually.
- $373.3 BILLION: total value of Texas projects stuck in the federal permitting process right now.
- $924.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Texas.
- The total economic impact of Texas projects entering the federal permitting process annually is equivalent to 11.6% of Texas’s total GDP.
- $1.4 BILLION: total cost of federal permitting delays to Texas manufacturers annually.
Utah:
- $25 BILLION: total value of Utah projects stuck in the federal permitting process right now.
- $54.4 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Utah.
- The total economic impact of Utah projects entering the federal permitting process annually is equivalent to 5.2% of Utah’s total GDP.
- $87 MILLION: total cost of federal permitting delays to Utah manufacturers annually.
- $3.4 BILLION: total value of Vermont projects stuck in the federal permitting process right now.
- $5.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Vermont.
- The total economic impact of Vermont projects entering the federal permitting process annually is equivalent to 3.1% of Vermont’s total GDP.
- $29 MILLION: total cost of federal permitting delays to Vermont manufacturers annually.
- $37.3 BILLION: total value of Virginia projects stuck in the federal permitting process right now.
- $66.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Virginia.
- The total economic impact of Virginia projects entering the federal permitting process annually is equivalent to 2.3% of Virginia’s total GDP.
- $199 MILLION: total cost of federal permitting delays to Virginia manufacturers annually.
- $30.2 BILLION: total value of Washington projects stuck in the federal permitting process right now.
- $63.5 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Washington.
- The total economic impact of Washington projects entering the federal permitting process annually is equivalent to 2.2% of Washington’s total GDP.
- $196 MILLION: total cost of federal permitting delays to Washington manufacturers annually.
- $22.3 BILLION: total value of West Virginia projects stuck in the federal permitting process right now.
- $32.6 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in West Virginia.
- The total economic impact of West Virginia projects entering the federal permitting process annually is equivalent to 9.4% of West Virginia’s total GDP.
- $87 MILLION: total cost of federal permitting delays to West Virginia manufacturers annually.
- $24 BILLION: total value of Wisconsin projects stuck in the federal permitting process right now.
- $46.8 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Wisconsin.
- The total economic impact of Wisconsin projects entering the federal permitting process annually is equivalent to 3.4% of Wisconsin’s total GDP.
- $339 MILLION: total cost of federal permitting delays to Wisconsin manufacturers annually.
- $20.6 BILLION: total value of Wyoming projects stuck in the federal permitting process right now.
- $29.3 BILLION: total economic impact (including jobs, in-state spending, tax revenue, and more) on hold due to the current federal permitting queue in Wyoming.
- The total economic impact of Wyoming projects entering the federal permitting process annually is equivalent to 17.9% of Wyoming’s total GDP.
- $35 MILLION: total cost of federal permitting delays to Wyoming manufacturers annually.
Nationwide:
- $240-280 BILLION in new investments begin the federal permitting process each year
- The current 4-5 year federal permitting decision timeline results in $1.7-2.4 TRILLION in unrealized economic benefit annually
- $1.1-1.5 TRILLION in investments are sitting on the sidelines waiting for permitting decisions
- $12.1 BILLION: total cost of federal permitting delays to America’s manufacturers annually