FOR IMMEDIATE RELEASE:
Contact:
Kristina Baum –
202.224.6176
Donelle Harder
– 202.224.1282
Sen.
Inhofe’s Statement on the U.S. Nuclear Regulatory Commission’s Completed
Technical Review
WASHINGTON, DC – U.S. Senator Jim Inhofe (R-Okla.), chairman of
the U.S. Senate Environment and Public Works Committee, released the following
statement upon the
U.S. Nuclear Regulatory Commission’s (NRC) completed technical review of
the Yucca Mountain repository license application:
“The
American people have spent 30 years and $15 billion to determine whether Yucca
Mountain would be a safe repository for our nation’s civilian and
defense-related nuclear waste. Four years ago, the Nuclear Regulatory
Commission’s review was illegally shutdown. Today, with the public
release of the last remaining volumes of the Safety Evaluation Report,
Americans will finally know the complete technical conclusion about the safety
of Yucca Mountain. Congress must now provide funding for the licensing
process to continue, and transfer control over the land and water rights to the
Department of Energy (DOE) to officially make Yucca Mountain a place to safely
contain our nation’s nuclear waste. I will work with my colleagues in the
Senate to ensure that America has a safe, permanent resting place for nuclear
waste.”
The complete
5-volume Safety Evaluation Report documents the NRC’s technical
conclusions, of which no safety concerns were highlighted that would prevent
NRC authorizing construction of the Yucca Mountain repository.
However, Congress would have to transfer control of the land where the
repository is located to DOE and provide water rights before NRC staff would
recommend issuing construction authorization, something widely known for
decades.
In
Volume 2, the NRC staff recommended certain licensing conditions including
requiring prior NRC approval before emplacement of certain types of fuel and
complete agreements for airspace restrictions to prevent overflights.
Such license conditions do not preclude construction authorization but
represent additional requirements DOE must meet. Volume 5 summarizes the
entire Safety Evaluation Report including findings, license conditions, and the
need for DOE to comply with the NRC’s requirements for land control and water
rights.
The next
steps in the Yucca Mountain licensing process include completion of the
Environmental Impact Statement, and the adjudication of stakeholder contentions
disputing various aspects of the application and the NRC staff’s conclusions.
The last step in the process is for the Commission itself to issue its decision
regarding authorization of repository construction.
###